A group-housing study needs a defined authority framework and building category before calculating capacity. Use the actual plot, road and verified controls to test one or more buildings, then report achieved floor area separately from theoretical FAR entitlement.

Start with classification and a source register

Do not classify a proposal as group housing merely because its plot exceeds a plotted-development band. Check the applicable definition, minimum site requirements and proposed use. For each control, retain the clause, inputs, exceptions and any interpretation that remains unresolved.

Keep the parking stilt separate from occupied floors

Under the supplied 2026 industrial-authority model, §3.3.4.8 allows parking stilt beyond group housing; the specific group-housing parking section refers back to it. Parking-only area is excluded from FAR but contributes to height. Ordinary height/headroom and separate stack-parking provisions need checking. This summary must not be applied to another framework by analogy.

Government of Uttar Pradesh / Invest UP · Base document ↗

Use one shared site allowance for several buildings

Sum the counted areas of all proposed buildings against one site FAR budget. Measure actual clear distances and review the applicable taller-building spacing rule. Setback, fire-access and park geometries are different controls; a coloured clearance band is not proof that an access route turns or reaches every required side.

Test stepped plates without assuming a tier exemption

A smaller upper plate may use residual FAR and create terraces. Show the plate dimensions, floor count and total height while retaining the required setback checks. The current prototype uses conservative whole-building height controls; it does not approve a separate lower setback for every tier.

What a paid feasibility report would still need

An architect should verify applicability, survey geometry, allotment terms, statutory restrictions and unresolved interpretations, then check access, parking and usable planning. The current tool has no professional sign-off or payment workflow. Its outputs are a starting scenario with evidence, not a sanction-ready report.

Common questions

Does the tool prove maximum buildable area?

No. It searches within stated geometry and floor assumptions and shows remaining allowance. Global optimisation and usable apartment planning have not been demonstrated.

Is stilt parking only for group housing?

Not in the supplied 2026 model. Its general stilt clause applies beyond group housing; verify the relevant document before using that rule elsewhere.

How this guide was checked

Links and document identity were checked against official publisher pages on 3 November 2026. This is source navigation and explanation, not an independently signed regulatory opinion. No complete amendment consolidation, parcel-specific local adoption review or professional sign-off is claimed. Numerical calculator coverage is stated separately.